Technip Geoproduction (M) Sdn Bhd
Manufacturing Workshop
The Major Building
The total weight of steel structure for Asiaflex project is 2100 tons and the Manufacturing Workshop is the major building in the whole project. There is 1200 tons of steel structure for this Manufacturing Workshop.
The gross area for Manufacturing Workshop is 135m x 96m with 6 nos of motorized sliding doors (14m x 14m) for entrance.
The sub-structures are of reinforced concrete structures and super-structures are of steel structures. The height of the building is ranging from 18.8m to 23m at pitch and the roof is using Lysaght Klip-Lok 406 system with rockwool insulation.